Hello,
I'm not sure if it's possible, but I'm being asked to show tracking of
Baseline Start vs. Actual Start bars on top of eachother. I know in tracking
gantt view, it shows these one below the other, but is it possible to show
them on top of eachother? hmmm.....
 
J

JulieS

Hi Jason,

See Format > Bar Styles. The bar shapes are what make the bars appear
to be one below another. If you change the bars to wider shapes, you
can make one appear over another.

I hope this helps. Let us know how you get along.

Julie