Project 2007: weekend-only calendar?

A

Abo

As per the title, really! I have some tasks which only occur on weekends,
and a 'weekend-only' team which will do them. It was simple to create a
'weekend only' calendar in Project 2003; is there a simple way of doing the
same in 2007?

Thanks
 
J

Jan De Messemaeker

Hi,

Not as simple, but still:

Tools
Change Working time
Select the resource
Click Work Weeks
Click details
set Sat/Sun to "... specific working times", click enter before hitting OK
Set Mo-Fri to "non working times"

There you are.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620