A
Abo
As per the title, really! I have some tasks which only occur on weekends,
and a 'weekend-only' team which will do them. It was simple to create a
'weekend only' calendar in Project 2003; is there a simple way of doing the
same in 2007?
Thanks
and a 'weekend-only' team which will do them. It was simple to create a
'weekend only' calendar in Project 2003; is there a simple way of doing the
same in 2007?
Thanks