Scenario
Project s scheduled from the start date
Project Start date is 1/19/10
Status date is set as 12/20/09
Now if we change the Status date to "NA" the tasks duration as well as the
start and finish date changes.
I want to change the Status date to "NA" without affecting duration or
sart/finish dates of the tasks