I just had Project 2007 installed and all my duration went from whole number
to decimals when I opened an existing schedule from Project 2003. Can anyone
inform me how to set the numbers to whole without effecting my original
durations or work hours????
 
J

Jan De Messemaeker

Hi,

Your Work hours won't have changed.
Your durations haven't changed either (Project stores everything in minutes)
but their expression in days may have changed because the definition of a
day may be different.
Check Tools, Options, Calendar and rest the hours per day to its previous
value.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
D

DBaddorf

Jan,

I followed your instructions and the calendar is set up the same (standard).
Is there a way in project to not have decimals in the durations?
 
J

Jan De Messemaeker

Hi,

I did not mention the calendar, I wrote Tools, Options, Calendar.
Did you have a look there?
And no, if the durations are not whole days, that will show

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 