T
Thomas Bräutigam
Hi all,
one question regarding the new Project 2010.
Is it possible to fix a maximum of hours for a task or assignment, so
that the budgte cannot be "over"-booked?
For example a resource has only 20hours for task A and so this
resource can max. book 20 hours or less to fulfill this task in the
timesheet!?
Regards
Thomas
one question regarding the new Project 2010.
Is it possible to fix a maximum of hours for a task or assignment, so
that the budgte cannot be "over"-booked?
For example a resource has only 20hours for task A and so this
resource can max. book 20 hours or less to fulfill this task in the
timesheet!?
Regards
Thomas