A
Anthony
When I publish an existing project plan to the project server (using the
import process), all the actual time entered in the project plan gets divided
into weird fractions for tasks. For example, if Task A has 10 hours for Work
entered and is imported, when I look at the time sheet for Task A, the 10
hours look like 2.3, 5.5, 2.2 spread out over several days or weeks. I just
want it to show that Task A, when imported, has 10 hours of actuals already,
and that any time entered from the PWA will append to the 10 hours. I don't
understand all this fraction of hours crap its doing. Thanks
import process), all the actual time entered in the project plan gets divided
into weird fractions for tasks. For example, if Task A has 10 hours for Work
entered and is imported, when I look at the time sheet for Task A, the 10
hours look like 2.3, 5.5, 2.2 spread out over several days or weeks. I just
want it to show that Task A, when imported, has 10 hours of actuals already,
and that any time entered from the PWA will append to the 10 hours. I don't
understand all this fraction of hours crap its doing. Thanks