J
Jack Shearer
I am trying to allocate a task which a team of three people will take 1 day
to complete when working together. One of the team has a Calendar which
allows him to work only on weekends.
Trouble is when I allocate the resources after setting the duration, project
resets the duration to several days and if I then reset the duration to 1
day, it recalculates two of the workers to zero time.
What do I need to do to get Progect to accept that it is three people
working 1 day and because 1 resource has a Calendar constrant that it needs
to set the date according to that Calendar?
Thanks in anticipation.
to complete when working together. One of the team has a Calendar which
allows him to work only on weekends.
Trouble is when I allocate the resources after setting the duration, project
resets the duration to several days and if I then reset the duration to 1
day, it recalculates two of the workers to zero time.
What do I need to do to get Progect to accept that it is three people
working 1 day and because 1 resource has a Calendar constrant that it needs
to set the date according to that Calendar?
Thanks in anticipation.