Project Analyser 'No Value'

P

PG

We have resources with a required RBS value for each and each has been
assigned. We have tasks that consume these resources.

Yes, when we look at the cube via a view or even directly using analysis
manager browse data, all the data appears in the "no value" row rather than
in a row for a given resource/rbs breakdown. Yes, we did to the manage
enterprise resource process to redo the resources.

One thing we did was add resources via Import and after doing this, we later
went back and created the RBS and assigned them. Essentially we did the rbs
"after the fact". Does this cause an inconsistency and if so -- how do we
recover?

Also our slicer is showing that our RBS is level 2 and level 3 but we only
have 2 levels. Is the convention that the level starts with 2? Is something
off here?
 