C
Chris
I am looking for a way to place more than one milestone on a single task
line? Background: I have modelled the schedule and have 10% / 50% / 90%
confidence values against each task finish date and would like to show this
information on my gantt chart. I'm using ms project 2003 professional and
have 2003 project server available.
Many thanks in advance
line? Background: I have modelled the schedule and have 10% / 50% / 90%
confidence values against each task finish date and would like to show this
information on my gantt chart. I'm using ms project 2003 professional and
have 2003 project server available.
Many thanks in advance