M
msnews.microsoft.com
Hi,
I have a problem that I am having trouble understanding.
I have defined portfolio Analyzer view to show actual work versus baseline
work, and actual work (cummulative) versus baseline work (cummulative). i.e.
to show monthly progress against the baseline.
Everything seems to work OK, from an OLAP perspective. However, my OLAP
baseline totals do not add up to the baseline in my project.
Total Baseline work in my project (as seen through statistics in Project
Pro) = 6300 hours
Total Baseline work as seen in the OLAP data = 4775.
How can these two be different?
How can I reconcile them to find out why they are different?
Cubes are updated daily at midnight so the cube should be up to date.
Thanks in advance
Simon
I have a problem that I am having trouble understanding.
I have defined portfolio Analyzer view to show actual work versus baseline
work, and actual work (cummulative) versus baseline work (cummulative). i.e.
to show monthly progress against the baseline.
Everything seems to work OK, from an OLAP perspective. However, my OLAP
baseline totals do not add up to the baseline in my project.
Total Baseline work in my project (as seen through statistics in Project
Pro) = 6300 hours
Total Baseline work as seen in the OLAP data = 4775.
How can these two be different?
How can I reconcile them to find out why they are different?
Cubes are updated daily at midnight so the cube should be up to date.
Thanks in advance