Steve
Does anyone know how to stop MS Project from doing this? Here's an example:
Let's say I have five tasks called Monday - Friday
Each task (day) is dependent on the previous one
I would expect that if I moved say Wednesday (which is a succesor to Tues)
to either the start or end of the WBS, that the Wed Task would still honor
the original dependency on Tuesday. however, it does not.
Let's say I have five tasks called Monday - Friday
Each task (day) is dependent on the previous one
I would expect that if I moved say Wednesday (which is a succesor to Tues)
to either the start or end of the WBS, that the Wed Task would still honor
the original dependency on Tuesday. however, it does not.