M
Mary
MS Project calculates a work variance by comparing baseline to
scheduled work. If I re-baseline my project, I would like to calculate
the work variance comparing the most current baseline (e.g., baseline
1) to the scheduled work. How can this be done and still retain
information about the original baseline?
scheduled work. If I re-baseline my project, I would like to calculate
the work variance comparing the most current baseline (e.g., baseline
1) to the scheduled work. How can this be done and still retain
information about the original baseline?