Project Budget Cost value inconsistent in Data Analysis

A

Avi

We are using Cost resources (6 at present) to enter Project Budget
Cost. We assign the cost resources to the Project summary tasks and
then enter budget cost against the 6 cost resources. All cost
resources then roll up to create the Project Budget cost.

I am running into an issue with Data Analysis cost fields where they
are doing some weird rounding. For example, in a sample project, right
now without any formatting Project Budget cost of $165,500 is showing
up as 165,499.37. If I use the currency formatting, it just adds a $
sign. I tried using $#,##0 formatting but using this results in
$165,499.

How can I have Data Analysis show the correct Budget cost $ figure as
entered in Project Pro i.e. in this case $165,500

We are using PS2007 SP1.
Thank you for your time in advance.

Avi
 