project calendar and mytask calendar are desynchronized

H

Hernandezz

Hi,

I have EPM 2007 and a strange problem, I think!!!

My issue is that the project calendar and mytask calendar are
desynchronized. Example,when I put 8h in "mytasks" on January 29, and
once they are approved, these 8h go to the plan on JAnuary 30. One
day forward.

I did a lot of tests, verified if there were other calendars besides
the standard one, but there weren't.

Any suggestion please?

cheers..
 
H

Hernandezz

Does this happen in all cases? Are you certain that you have January 29 as a
working day in the standard calendar?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting:http://www.msprojectexperts.com
Project Server Training:http://www.projectservertraining.com
Project Server FAQS:http://www.projectserverexperts.com
Project Server Help Blog:http://www.projectserverhelp.com

this only happens in this project, and the work days in calendar are
correct. This happens not only in 29 January, but in all project,
example I put 8h in day 3 and the hours in the project go to day 4 and
so one.

I try copy this project to other, (save as) but the problem continuos.

What do you sugere, create a new project?

cheers
 
G

Gary L. Chefetz

Do the settings in Project from Tools > Options > Calendar tab for "Week
Starts On" agree with the settings in Project Server Server Settings > Time
and Task Mangement > Task Settings and Display "Weeks Starts On?" That's
the only other thing I can think of, and I'm not sure that it could be the
cause, otherwise it could very well be corruption in the file. In this case,
save the project as XML and reimport it to Project Server after deleting the
original.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Does this happen in all cases? Are you certain that you have January 29 as
a
working day in the standard calendar?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting:http://www.msprojectexperts.com
Project Server Training:http://www.projectservertraining.com
Project Server FAQS:http://www.projectserverexperts.com
Project Server Help Blog:http://www.projectserverhelp.com

this only happens in this project, and the work days in calendar are
correct. This happens not only in 29 January, but in all project,
example I put 8h in day 3 and the hours in the project go to day 4 and
so one.

I try copy this project to other, (save as) but the problem continuos.

What do you sugere, create a new project?

cheers
 