H
Hernandezz
Hi,
I have EPM 2007 and a strange problem, I think!!!
My issue is that the project calendar and mytask calendar are
desynchronized. Example,when I put 8h in "mytasks" on January 29, and
once they are approved, these 8h go to the plan on JAnuary 30. One
day forward.
I did a lot of tests, verified if there were other calendars besides
the standard one, but there weren't.
Any suggestion please?
cheers..
I have EPM 2007 and a strange problem, I think!!!
My issue is that the project calendar and mytask calendar are
desynchronized. Example,when I put 8h in "mytasks" on January 29, and
once they are approved, these 8h go to the plan on JAnuary 30. One
day forward.
I did a lot of tests, verified if there were other calendars besides
the standard one, but there weren't.
Any suggestion please?
cheers..