Week-end Work day Exceptions in EPM
I have tried to change the working time in the project calendar - performed
the ms project tools procedure to do so. The problem is when I did, it
changed my entire project plan because it assumes that these working days are
valid for the entire plan so it adjusted the start and end dates for my
tasks. I want to specifically change the working time for a few tasks – not
all of them – and this is where I have a problem because I can’t seem to do
this.
Can someone help?
Baffled...MK