C
careta
Hi,
I configured a custom calendar with all Sundays be working days and
Fridays be non-working days, and assigned it a name. Then, I
configured my project to use this calendar. Now, when I add tasks,
they use Friday as a working day (wrong), Saturday as non-working
(default) and Sunday as working day (correct). Looking at the task
info (advanced tab), all tasks appear as using no calendar (none).
Only when I specify for each task that it should use the custom
calendar (the one I configured my project to use), it works ok. This
is quite annoying, 'cause it forces me to remember to apply the custom
calendar for each new task I add, and causes errors when I forget to
do so.
Thanks!
careta
I configured a custom calendar with all Sundays be working days and
Fridays be non-working days, and assigned it a name. Then, I
configured my project to use this calendar. Now, when I add tasks,
they use Friday as a working day (wrong), Saturday as non-working
(default) and Sunday as working day (correct). Looking at the task
info (advanced tab), all tasks appear as using no calendar (none).
Only when I specify for each task that it should use the custom
calendar (the one I configured my project to use), it works ok. This
is quite annoying, 'cause it forces me to remember to apply the custom
calendar for each new task I add, and causes errors when I forget to
do so.
Thanks!
careta