A
Anum_10
We have Project Server 2007.
Our Project Calender in Project Professional is not taken the precedence
over the Resource Calendar.
Project Calendar used to take precedance over Resource and Task Calendar,
but now the Resouce Calendar is taking the precedance. As soon as we assign
the resources to the task, the tasks are no longer displayed by the project
calendar dates, they are now displayed by resource calendars.
What are we doing wrong? Please advise. Thanks!
Our Project Calender in Project Professional is not taken the precedence
over the Resource Calendar.
Project Calendar used to take precedance over Resource and Task Calendar,
but now the Resouce Calendar is taking the precedance. As soon as we assign
the resources to the task, the tasks are no longer displayed by the project
calendar dates, they are now displayed by resource calendars.
What are we doing wrong? Please advise. Thanks!