T
Todd
Hi,
I am having an issue with calendars that I hope someone can help me
with. We have projects in both Canada and the US. The calendars for
these countries are different (obviously with holidays and such),
however, the resources may work on both of sets of projects.
becomes a problem when I have a US resource on a Canadian project and
vice versa. For instance, there may be days off on the Canadian
project that I don't want the US resource to work, but I also don't
want to block that day off his calendar because I may want to assign
him a task on a US project.
Is there any way to specify using the project calendar above the
resource calendar on a project? Or has anyone else run into this
problem and come up with a solution?
Thanks!
Todd
I am having an issue with calendars that I hope someone can help me
with. We have projects in both Canada and the US. The calendars for
these countries are different (obviously with holidays and such),
however, the resources may work on both of sets of projects.
resource's calendar is the one that takes precedent on a task. ThisFrom what I've read, when you assign a resource to a project, that
becomes a problem when I have a US resource on a Canadian project and
vice versa. For instance, there may be days off on the Canadian
project that I don't want the US resource to work, but I also don't
want to block that day off his calendar because I may want to assign
him a task on a US project.
Is there any way to specify using the project calendar above the
resource calendar on a project? Or has anyone else run into this
problem and come up with a solution?
Thanks!
Todd