G
Guest
Hi,
I work with MS Projecr 2003 standard.
I have set up a group of subprojects, one file each. They
all work with one resourcepool.
I have defined an projectcalender for the project. I
defined it in projectinformation - projectcalender. The
whole july is working days. BUT the program still set all
days in july as not working days. The program seems to
look at the standard calender in some way.
Can anyone give me a tip ?
/Lennart
I work with MS Projecr 2003 standard.
I have set up a group of subprojects, one file each. They
all work with one resourcepool.
I have defined an projectcalender for the project. I
defined it in projectinformation - projectcalender. The
whole july is working days. BUT the program still set all
days in july as not working days. The program seems to
look at the standard calender in some way.
Can anyone give me a tip ?
/Lennart