N
nosrednag
I have a masterz project, really a project list, and each "task" is the
collapsed first line of ongoing active projects. I want to show only the
first line of each working project on the master list, and not all the
underlying detail...can I lock the task so it cannot be expanded for
management view, but still provide updating when the working projects are
updated? I just want to show management the duration of the project only,
not sub-tasks...
collapsed first line of ongoing active projects. I want to show only the
first line of each working project on the master list, and not all the
underlying detail...can I lock the task so it cannot be expanded for
management view, but still provide updating when the working projects are
updated? I just want to show management the duration of the project only,
not sub-tasks...