S
ss028955
I have created views in Project Center which contains Projects, Proposals and
Activities
The Problem is;
My Actual cost and Actual Duration columns are showing 0 and Remaining
Duration and Remaining Cost columns are showing estimated Duration and
estimated Cost. As it supposed to pick up total logged time from timesheet.
Can someone help?
Regards
ss028955
Activities
The Problem is;
My Actual cost and Actual Duration columns are showing 0 and Remaining
Duration and Remaining Cost columns are showing estimated Duration and
estimated Cost. As it supposed to pick up total logged time from timesheet.
Can someone help?
Regards
ss028955