Project Center Date Format

E

eReader

Hi All,

Project Web Access 2003 web interface with Microsoft Project Server 2003 on
Windows Server 2003 Standard Edition Machine

On Project Web Access under the project center view,

I want to change the date format for "Start" Date & "Finish" Date column

from 2/3/05 to ==>>> 2nd May, 2005


How can we acheive this

kindly help
 
E

eReader

Its a date which comes in the PWA grid for a projects in a Summary View

It's showing numeric date how can i change it to the mentioned format

2nd May, 2005 or May 2 , 2005
 
E

elvira

I have the same question. I tried to do this with Porfolio analyser
view, but no result.
For me it would also be okay if I can show the weekend days in a
different format.
Ideas anyone?
 
J

Jonathan Sofer - MCP

Hi eReader and Elvira,

Here is a solution that works but requires the use of a Project Level
Custom Text field.

1) Log into Project Pro as an administrator
2) Open up the Enterprise global: Tools>Enterprise Options>Open
Enterprise Global
3) Go to Tools>Customize>Enterprise Fields...
4) Naviaget to Custom Project Text fields.
5) Take the next available Text Field and rename it "Starts" you need
the 's' at the end because you can't have two fields with the same
value and Start already exists.
6) Click the Formula button and put the following in:
[Start]
7) Do the same thing for Finish with the next available Text Field,
renaming it "Finishes" and the making the formula:
[Finish]
8) Save and Close the Enterprise Global file.
9) Exit Project Professional
10) Log back into project professional to load the latest enterprise
global.
11) For all projects you want this to effect you will have to open up
the proejct and do a Collaborate>Publish>All Information
12) In PWA you will need to add Starts and Finishes to the Project
Center Views and move the Start and Finish columns to the end since you
cannot remove Start and Finish from the Project Center views. You can
make Start and Finish a fixed width of 1 pixel to hide it.
13) This will now show in Project Center for all projects a Starts and
Finishes column with the date and the day of the week.

Pretty elaborate and I know you were looking for something more
straightforward. I do not know of any.
 
E

eReader

Thanks for the idea but it didn't work, displaying NA in Starts and Finishes
column
 
J

Jonathan Sofer - MCP

Make sure you open each project, insert the new project text column on the
project plan to make sure it is showing the correct date value to get the
data out there or else you will see nothing or an error. Then when you save
and close it will push the new data out.

If you do not have auto calculate on in Tools>Options>Calculation tab then
you will have to hit F9 to calculate the new value. From then on if the
Start of Finish date changes in the project plan, the new date will be
pushed out to the Starts and Finishes every time the project is Saved.

I tested it last night before I sent the instructions to you and it worked
fine. I can send you the screen shot if you like.

--
Jonathan Sofer - MCP
PM Consultant
PCubed - Program Planning Professionals
--
eReader said:
Thanks for the idea but it didn't work, displaying NA in Starts and
Finishes
column

Jonathan Sofer - MCP said:
Hi eReader and Elvira,

Here is a solution that works but requires the use of a Project Level
Custom Text field.

1) Log into Project Pro as an administrator
2) Open up the Enterprise global: Tools>Enterprise Options>Open
Enterprise Global
3) Go to Tools>Customize>Enterprise Fields...
4) Naviaget to Custom Project Text fields.
5) Take the next available Text Field and rename it "Starts" you need
the 's' at the end because you can't have two fields with the same
value and Start already exists.
6) Click the Formula button and put the following in:
[Start]
7) Do the same thing for Finish with the next available Text Field,
renaming it "Finishes" and the making the formula:
[Finish]
8) Save and Close the Enterprise Global file.
9) Exit Project Professional
10) Log back into project professional to load the latest enterprise
global.
11) For all projects you want this to effect you will have to open up
the proejct and do a Collaborate>Publish>All Information
12) In PWA you will need to add Starts and Finishes to the Project
Center Views and move the Start and Finish columns to the end since you
cannot remove Start and Finish from the Project Center views. You can
make Start and Finish a fixed width of 1 pixel to hide it.
13) This will now show in Project Center for all projects a Starts and
Finishes column with the date and the day of the week.

Pretty elaborate and I know you were looking for something more
straightforward. I do not know of any.
 
E

Elvira

Jonathan, thank you for your reply. I have tested it and it works fine.

I realise that I have a slightly different question, I was not detailed
enough in my explanation, sorry. I was wondering how I can show the
date (with the day of the week) in for example the view Resources >
Summary view. I can see the days of the week when I select one week,
but when I select 3 or 4 weeks the days dissapear. The selection of 3
or 4 weeks is used much more often within my company.
Do you have ideas for this as well?

Elvira
 
J

Jonathan Sofer - MCP

Sadly, I do not know of a way to display days in the assignment view if the
number of days goes over 7. I believe it would require customization.

You could possibly export the view to Excel directly from that screen and
manipulate the date there to show day of the week. You could even have a
macro do it for you quickly.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top