Scott Morrissey
When you define project center views, how do you modify the look of the Gantt
Chart on the right-hand side of the window? In the Admin function to modify a
view, it gives a drop-down list box of which Gantt Chart format to use. I've
tried all of them and none of them seem to make a difference. Where can these
be modified?
What I want to change is the TIMESCALE on the Gantt Chart. Every view I see
is by DAY. We need a higher-level timescale to show by Month or by Week so
that you can get a better view of the entire project.