P
Peggy Cornett
MS Project 2003 (11.2.2005.1801.15) SP2 Project Server 2003 SP2
Currently I have a view in Project Center that will work well for a monthly
meeting we have. The projects are statused weekly. We have this meeting mid
month to review the previous fiscal month project schedules. By that time
the view that would work well now has current information since they have
been statused weekly. I want to have this view to reflect the project
information as it was at month end. Is the best way to do this is add a
version and at the end of each month save a copy with this version and then
have my view filtered only to include this version? I would want to
overwrite these each month end as to not clutter up the server. I could do
something like this as well with a master project but I would still have the
issue of needing to have a snapshot of the schedule as it is at month end.
Currently we do not use versions, only published.
Thank you,
Peggy Cornett
Currently I have a view in Project Center that will work well for a monthly
meeting we have. The projects are statused weekly. We have this meeting mid
month to review the previous fiscal month project schedules. By that time
the view that would work well now has current information since they have
been statused weekly. I want to have this view to reflect the project
information as it was at month end. Is the best way to do this is add a
version and at the end of each month save a copy with this version and then
have my view filtered only to include this version? I would want to
overwrite these each month end as to not clutter up the server. I could do
something like this as well with a master project but I would still have the
issue of needing to have a snapshot of the schedule as it is at month end.
Currently we do not use versions, only published.
Thank you,
Peggy Cornett