In all Project Center detail views, the right-hand pannels show data in a
gantt chart. Is there a way to put a time-phased view here instead of a gantt
chart? For example, show work hours by week for the next several weeks?
 
M

Marc Soester

Hi Scott,

Sorry not in project center. This is a limitation of the product. What you
can do is only give 1 pixel to the gantt chart and have more colums on your
left grid.

hope this helps
 