W
wacNTN
We have about 200 projects and our Project Center views are all slow to load.
The Resource Center views and Project Analyzer all come up quickly.
Over the 200 projects there are a TOTAL of about 3500 assignments in the
system. (We are just getting started.)
All of this is on the same machine right now. The O/S is Windows 2003,
quad processor, 3.4 GHz, 3 GB RAM, Project Server has access to 12GB of
storage.
The number of tasks per project is anything from 1 or 2 to 500 but probably
more in the 50 per project average.
We have fewer than 5 regular users of the system right now with about 150
resources loaded.
This problem occurs on multiple workstations for multiple users. We're
about to ramp up use so we need to resolve this.
Any ideas on how to improve the Project Center views' performance?
Thanks,
Walter
The Resource Center views and Project Analyzer all come up quickly.
Over the 200 projects there are a TOTAL of about 3500 assignments in the
system. (We are just getting started.)
All of this is on the same machine right now. The O/S is Windows 2003,
quad processor, 3.4 GHz, 3 GB RAM, Project Server has access to 12GB of
storage.
The number of tasks per project is anything from 1 or 2 to 500 but probably
more in the 50 per project average.
We have fewer than 5 regular users of the system right now with about 150
resources loaded.
This problem occurs on multiple workstations for multiple users. We're
about to ramp up use so we need to resolve this.
Any ideas on how to improve the Project Center views' performance?
Thanks,
Walter