When I look at certain columns in any of the project centre views eg.
Work, Remaining Work they display as hours... I need them to display in
days. I've had a look at the Manage Views setup but I can't seem to
find a setting to change so that they display in days.

I would really appreciate any help. Thank you.

Rosa
 
M

Marc S.

Rosa,

Unfortunately in Project Server 2003 it is not possible to change units for
work, actual work, remaining work etc. If you want them displayed in days
rather than hours you will have to set up a new field in your Enterprise
Global and automatically calculate the value in days: work in hours :8 = work
in days.

Hope this helps...

Marc
 
R

riccadonna63

Thank you Marc... I guess this will give everyone good practice with
their 8 division table

Cheers
Rosa
 
T

The_Human_Torch

Rosa

You could create a custom enterprise number code that does a simple
formula - such as Enterprise Number Code 1 = Work/number of hours in
day - "number of hours in day" is a field you can select or you could
use 8 - but if this ever changes then all your calcs would be wrong.

You could then include this new enterprise code in your project center
view along side or in place of the work field.

Hope this helps
 