Not puzzling, kinetix, just that I suspect you have a mis-match with times. First, go to Tools/Options/View tab and at the top select a Date format so that it includes times. Now check your Start dates to ensure they start at the beginning of the day - it defaults to 0800 - but as you didn't say what changes you made for a 10 hour day or where you changed them I can't be exact. See that the Finish times are all 19:00 or at whatever end time you've set for the working day. If they're are not correct, re-set your calendar via Tools/Change Working Time (it is better to make a copy of the standard calendar to keep the original for later use). Now make sure you have set your times in Tools/Options/Calendar tab to match. Finally check that Project/Project Information uses the calendar you've edited and that it shows a start time the same as you've just set for the start of the day (if not just type in the date and time you want).
You might like to see FAQ Item: 5. Default Working Hours. FAQs, companion products and other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm.
Incidentally, the only date you should be typing in is the Project Start Date. Then enter the tasks names and durations. Then enter the precedence links (logic links) to let Project do what you've bought it for: to drive the start and finish dates and calculate the schedule for you. Use Constraints very sparingly as each one reduces the flexibility you have to create a workable schedule.
Hope this helps - please let us know how you get on
Mike Glen
Project MVP
See
http://tinyurl.com/2xbhc for my free Project Tutorials
Hi Glen, I haven't been able to find why the program insists on
stretching the finish date. In the the 5 tasks I've pasted below, the
first three tasks are concurrent and have ASAP FS relationships with the
same single predecessor. The calendar is 4d, 10hr/d so 11/20 is a
no-work day. 3d starting 11/16 should finish 11/19. However, if I set
the constraint to must start on 11/16, it does finish 11/19 and change
the constraint back to ASAP it goes back to 11/23 finish. Puzzling???
Here are the tasks (sorry they run together)
Building 710 Provide/Install Piping wiring & Global
Controller 11/16/09 3 d 11/23/09
Building 725 Provide/Install Piping wiring & Global
Controller 11/16/09 3 d 11/23/09
Building 791 Provide/Install Piping wiring & Global
Controller 11/16/09 3 d 11/23/09
Tie-in power/communication Group 1 (Non-Nuke) 11/23/09 1 d 11/24/09
Global Controller programming & checkout Group 1 (Non-Nuke) 11/24/09 1
d 11/25/09