When making changes to a task, predecesor changes as expected. If I undo the
change, and make another change to that task, it ignores all of the
predecessors. I need to exit and open again to get the predecessors to work.
Is there some reason for this behavior? We are using Project Server so is it
possible this has something to do with this? Any advice would be appreciated.
 
M

Mike Glen

Hi chicagohunter ,

Try posting on the microsoft.public.project.server newsgroup (forum).
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 