G
Giovanni
Hi all,
2 PROBLEMS:
Using Project Server 2003 and Project Professional 2003, when a
resource charge worked hours on a project, using PWA, then, when the
PM approves worked hours, Project Server 2003 opens Project
Professional and updates the GANTT with Actual Work.
But, if actual Work is different from the planned work it
redistributes hours of the planned work. (First Problem)
If the task on which hours are charged is a Fixed Duration task, and
the resource begins to insert worked hours not from the Fixed Start
Date of the task, Project shift the beginning date of the task to the
first date on which hours are inserted (Second Problem).
Does anyone has done any customization inserting code that avoid this
behaviors?
Or, does anyone has experience of how much time could be necessary to
modify these behaviors of Project?
Thanks,
Giovanni
2 PROBLEMS:
Using Project Server 2003 and Project Professional 2003, when a
resource charge worked hours on a project, using PWA, then, when the
PM approves worked hours, Project Server 2003 opens Project
Professional and updates the GANTT with Actual Work.
But, if actual Work is different from the planned work it
redistributes hours of the planned work. (First Problem)
If the task on which hours are charged is a Fixed Duration task, and
the resource begins to insert worked hours not from the Fixed Start
Date of the task, Project shift the beginning date of the task to the
first date on which hours are inserted (Second Problem).
Does anyone has done any customization inserting code that avoid this
behaviors?
Or, does anyone has experience of how much time could be necessary to
modify these behaviors of Project?
Thanks,
Giovanni