Project cost at specific date range

  • Thread starter Mindaugas Bliûdþius
  • Start date
M

Mindaugas Bliûdþius

How can i report how much project cost for me from "date 1 " to "date 2".
 
J

JimS

You could go into the task usage view and look at the actual cost value in
the timebased data section. This should be rolled up and available to a top
level task.
 
S

Steve House [MVP]

After saving a baseline the Earned Value metric BCWS shows the cost of the
work planned up to the specified status date. After posting progress
against the project, ACWP shows the amount you've actually spent up to that
date. Depending on whether you're asking for projected costs or actual
costs in your question, I would simply use the Earned Value tables and look
up first the BCWS and ACWP for Date1 and then the same for Date 2.
Subtracting BCWS1 from BCWS2 gives you the planned expenditure between the
two dates while subtracting ACWP1 from ACWP2 gives you the actual amount
you've spent between the two dates.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top