Project creating via PWA

A

Andrzej Jaworek

When I create an enterprise project (this is the project that is edited
in Project 2007) I can decide which method I will use to allow users to
report the progress on tasks. But for operations work project (that
project is fully edited via PWA) there is only one method assigned:
percent of work complete. Why? This is a bug? Can I change this method
for operations work projects to of work done per day or week?

Andy
 
P

Paul Conroy

This "light weight" project feature is by design. If you require the ability
to change the tracking method then you will need to promote it to a fully
fledged project.