R
Risa
Hi all,
I'm using option move of completed parts after status date back to status
date. Project uses current date as status date. However by default current
date is current date 8:00am this cause the completed parts of tasks move
before current date 8:00am what practically means it is moved to
yesterday(default start time is 9:00am). I need to have current date set to
current date 17:00am so that completed parts are moved to current day before
17:00. If I set manually the current date to the current date 17:00, it
works ok, but when I open project next day, the current date is set again to
8:00am. Is there a way how to keep the 17:00 as a default time for current
date field?
thanks
I'm using option move of completed parts after status date back to status
date. Project uses current date as status date. However by default current
date is current date 8:00am this cause the completed parts of tasks move
before current date 8:00am what practically means it is moved to
yesterday(default start time is 9:00am). I need to have current date set to
current date 17:00am so that completed parts are moved to current day before
17:00. If I set manually the current date to the current date 17:00, it
works ok, but when I open project next day, the current date is set again to
8:00am. Is there a way how to keep the 17:00 as a default time for current
date field?
thanks