V
Vit @ OZ
Hello,
I'm trying to customize a field on project level…
The field have to show if a project has been updated or not o the last 14
days…
I’m using Project Server 2003, Project Professional 2003 and PWA 2003.
Here you are the step that I have followed:
1) Opened Project Professional 2003
2) Opened Enterprise Global (Tool -> Enterprise Options -> Open
Enterprise Global)
3) Opened Enterprise Fields (Tool -> Customise -> Enterprise Fields…)
4) Selected “Projectâ€
5) Selected “Textâ€
6) Inserted the following formula: IIf(DateDiff("d",[Last Update],
[Current Date])>=14,"Update Required","Current")
The problem is that the Project Fields Seems not to be updated….
On the PWA view, for example, there is the following information:
Project Test
Last Modified: 30/04/2008
Last Published: 30/04/2008
Custom Field: Updated Required
But today is the 8th of May, so it have to be “Currentâ€!!!
I have check also on the Project Information (in Project Professional,
Project -> Project Information…), and unfortunately, the custom field value
is “Updated Requiredâ€â€¦
What’s wrong??
Where can I check “Last Modified Dateâ€, “Last Update Date†and “Last
Published Date†in Project Professional??
Thank you so much to every body will be able to help me…
Regards
Vit
I'm trying to customize a field on project level…
The field have to show if a project has been updated or not o the last 14
days…
I’m using Project Server 2003, Project Professional 2003 and PWA 2003.
Here you are the step that I have followed:
1) Opened Project Professional 2003
2) Opened Enterprise Global (Tool -> Enterprise Options -> Open
Enterprise Global)
3) Opened Enterprise Fields (Tool -> Customise -> Enterprise Fields…)
4) Selected “Projectâ€
5) Selected “Textâ€
6) Inserted the following formula: IIf(DateDiff("d",[Last Update],
[Current Date])>=14,"Update Required","Current")
The problem is that the Project Fields Seems not to be updated….
On the PWA view, for example, there is the following information:
Project Test
Last Modified: 30/04/2008
Last Published: 30/04/2008
Custom Field: Updated Required
But today is the 8th of May, so it have to be “Currentâ€!!!
I have check also on the Project Information (in Project Professional,
Project -> Project Information…), and unfortunately, the custom field value
is “Updated Requiredâ€â€¦
What’s wrong??
Where can I check “Last Modified Dateâ€, “Last Update Date†and “Last
Published Date†in Project Professional??
Thank you so much to every body will be able to help me…
Regards
Vit