C
CyberSpider
Hi;
I am using project 2000. I am exporting data from Access database to a
project database MPD. My finish dates look something like this;
finish:7/8/2004
finish:8/3/2004
finish:8/17/2004
the start date should always be the previous end date so that the start and
finish dates should look like this;
s 7/8/2004 f 7/8/2004
s 7/8/2004 f 8/3/2004
s 8/3/2004 f 8/17/2004
but no matter what I do project subtracts 1 day from the finish date. The
program is not allowing me to make the finish date equal the next start
date. There are no links.
HELP
I am using project 2000. I am exporting data from Access database to a
project database MPD. My finish dates look something like this;
finish:7/8/2004
finish:8/3/2004
finish:8/17/2004
the start date should always be the previous end date so that the start and
finish dates should look like this;
s 7/8/2004 f 7/8/2004
s 7/8/2004 f 8/3/2004
s 8/3/2004 f 8/17/2004
but no matter what I do project subtracts 1 day from the finish date. The
program is not allowing me to make the finish date equal the next start
date. There are no links.
HELP