I am using project 2000. I am exporting data from Access database to a
project database MPD. My finish dates look something like this;
finish:7/8/2004
finish:8/3/2004
finish:8/17/2004

the start date should always be the previous end date so that the start and
finish dates should look like this;

s 7/8/2004 f 7/8/2004
s 7/8/2004 f 8/3/2004
s 8/3/2004 f 8/17/2004

but no matter what I do project subtracts 1 day from the finish date. The
program is not allowing me to make the finish date equal the next start
date. There are no links.

HELP
 
J

JackD

You need to be more precise here. Project schedules to the minute. Your date
needs to include the minutes as well. If a task (using the default standard
calendar) ends at 5:00PM 7/8/2004, the successor to that task will start at
8:00AM 7/9/2004.

Likewise a task that starts on 7/8/2004 and ends on 7/8/2004 typically has a
duration of 1 day, but a one day task can start on 7/8/2004 and finish on
7/9/2004 depending on when precisely it starts.

-Jack
 