A
arcticgoldfish
I'm using Project 2003. I have several tasks that link to another single
task (using finish-finish). However, because the dependency lines are all at
the same angle, you can't always see which tasks are linked (unless you read
the predecessor column). Is there a way of staggering the links, but leaving
them still pointing back to the finish of another task?
task (using finish-finish). However, because the dependency lines are all at
the same angle, you can't always see which tasks are linked (unless you read
the predecessor column). Is there a way of staggering the links, but leaving
them still pointing back to the finish of another task?