K
karishma
i am using MSP 2003. i have listed my summary tasks and subtasks as well. but
when i enter the start dates in subtasks it automatically enters finish dates
as per the mentioned duration. after entering duration and start dates for
all subtasks and predecessors as well, it shows the duration of the summary
task with decimal poiints.
can i hvae the solution for it? in some summary tasks it is giving roound
figure and in some cases it is showing durations with decimals.
is there any way to sort this out?
thanks
when i enter the start dates in subtasks it automatically enters finish dates
as per the mentioned duration. after entering duration and start dates for
all subtasks and predecessors as well, it shows the duration of the summary
task with decimal poiints.
can i hvae the solution for it? in some summary tasks it is giving roound
figure and in some cases it is showing durations with decimals.
is there any way to sort this out?
thanks