Project enterprise fields - Calculated Values

S

Scott

I am trying to shows some calculated values in the enterprise Project feilds,
so that I can disply them on Project views in Project Center.
specifically,

I want to calculate EAC using a differnt method than what is included in
Project.
I have entered the formula in to the Project Enterprise feild, both cost and
number. The formula uses the ACWP, Baseline cost and BCWP to do the
calculation.
However when i add the feilds to my project center view the caluations show
zero.
Am I doing something wrong here, can you do calcs in these fields.
i would also like to add a graphical indicator for CPI and SPI in the same
view. If I make one of the Project enterprise feilds = [CPI] is does not show
the correct value.
what am i doing wrong

thanks

Scott
 
M

Marc Soester

Hi Scott,
Additionally to your change in Project Web Access you will need to open
Project Professional, open your projects and press F9 ( recalculate). After
that you will need to republish your project. Only after you have done this
with your projects, you are able to see the values in Project Web Access.
I hope that helps
 
R

Reino Schneidergros

Also, an important note:

to see custom project fields in Portfolio Analyzer you will need this tool:
http://www.bogdanov-associates.com/eng.asp?rubr_id=484

Regards,
Reino


Marc Soester said:
Hi Scott,
Additionally to your change in Project Web Access you will need to open
Project Professional, open your projects and press F9 ( recalculate).
After
that you will need to republish your project. Only after you have done
this
with your projects, you are able to see the values in Project Web Access.
I hope that helps
--
Marc Soester
Program Manager &
Senior Product Specialist


Scott said:
I am trying to shows some calculated values in the enterprise Project
feilds,
so that I can disply them on Project views in Project Center.
specifically,

I want to calculate EAC using a differnt method than what is included in
Project.
I have entered the formula in to the Project Enterprise feild, both cost
and
number. The formula uses the ACWP, Baseline cost and BCWP to do the
calculation.
However when i add the feilds to my project center view the caluations
show
zero.
Am I doing something wrong here, can you do calcs in these fields.
i would also like to add a graphical indicator for CPI and SPI in the
same
view. If I make one of the Project enterprise feilds = [CPI] is does not
show
the correct value.
what am i doing wrong

thanks

Scott
 