Project Filters not working

S

SJ

All

I have the following filter setup

Name - * Tasks due as of today not completed
Conditions
FINISH is less than or equal to "Show tasks
that start or finish after:"?
AND %COMPLETE is less than 100%

When I apply this Filter the tasks in the last 2 phases of a 4 phase
project do not show up even though the conditions are valid.

I checked the Views, Tables, Groups for any conditions & found none.
Not sure where the issues is - any ideas

SJ
 
J

JackD

What date are you putting in?
Is the project fully expanded before you run this filter?

-Jack Dahlgren
 
A

aaren

I faced a similar issue. As a last resort, I deleted the filter and
rewrote the filter and then it started working. All the conditions
that you mentioned were applicable in my case. HTH.

aaren.
 