D
David Luper
Hi all!
I am working on a new report, and I need some formula help.
Essentially, we want Physical % Complete to be a weighted value driven by
the completion of project "gates" determined by entering a date value. We
will use this Physicial % Complete value for custom Earned Value calculations.
So, here is where I am -
I have created four custom date fields (Date1 through Date4). I intend to
have the PMs enter dates into these fields when the tasks (which are really
deliverables) are complete. I want each to kick off a certain amount of %
complete (i.e., Date1 = 50%, Date2=25% (a total of 75%), Date3=10% (a total
of 85%) and so on. Otherwise, the value in the field would be N/A. I want
the Physical % Complete to automatically generate and sum up in the summary
tasks when dates are entered into Date1-Date4.
I have tried IIf and CountAs functions, and they don't deliver the results I
want (although it is highly possible I am doing it incorrectly).
Any help would be appreciated!
Thanks!
David
I am working on a new report, and I need some formula help.
Essentially, we want Physical % Complete to be a weighted value driven by
the completion of project "gates" determined by entering a date value. We
will use this Physicial % Complete value for custom Earned Value calculations.
So, here is where I am -
I have created four custom date fields (Date1 through Date4). I intend to
have the PMs enter dates into these fields when the tasks (which are really
deliverables) are complete. I want each to kick off a certain amount of %
complete (i.e., Date1 = 50%, Date2=25% (a total of 75%), Date3=10% (a total
of 85%) and so on. Otherwise, the value in the field would be N/A. I want
the Physical % Complete to automatically generate and sum up in the summary
tasks when dates are entered into Date1-Date4.
I have tried IIf and CountAs functions, and they don't deliver the results I
want (although it is highly possible I am doing it incorrectly).
Any help would be appreciated!
Thanks!
David