L
Lamby74
I am evaluating Project 2003 as potential PM software for
an engineering group of a large company.
I will admit right away that I am new to Project, and am
likely ignorant of certain features and options the
software has, and I am only beginning to really understand
how the software functions (how it "thinks").
My problem is that I do not trust Project. I do not trust
that the reports (which are very nice, though I am
disappointed that there is no report-builder function) are
accurate.
I can enter data for a Resource (an engineer in my case).
For example, I want him to work for one hour on Task 1.
Sometimes Project will schedule my engineer for 6 minutes
per hour for six hours! Sometimes project will schedule
him in for repeating one hour increments all day (when it
is only a one hour task. It can't seem to manage such
simple things - it wants to make everything complicated.
It has a mind of it's own. I don't control it - it
controls me (or tries to! ;-). I don't like that about
Project one bit. Is there any way to get it to stop
rearranging my resources? Also, it will insist I have a
resource conflict, when in reality there is none. When I
try to change the software to match reality, either it
won't let me, OR it changes the data I enter to some crazy
number.
I have varied from effort driven, to un-checking that box
on each task, but that makes no difference. Also, I have
tried changing the task type - from fixed
work-duration-units. No help.
More knowledgeable users, please advise me. What am I not
doing? What am I doing wrong. I'd like to give Project a
fair shake, but right now, IMHO, it's like the QuickBooks
of PM software!
an engineering group of a large company.
I will admit right away that I am new to Project, and am
likely ignorant of certain features and options the
software has, and I am only beginning to really understand
how the software functions (how it "thinks").
My problem is that I do not trust Project. I do not trust
that the reports (which are very nice, though I am
disappointed that there is no report-builder function) are
accurate.
I can enter data for a Resource (an engineer in my case).
For example, I want him to work for one hour on Task 1.
Sometimes Project will schedule my engineer for 6 minutes
per hour for six hours! Sometimes project will schedule
him in for repeating one hour increments all day (when it
is only a one hour task. It can't seem to manage such
simple things - it wants to make everything complicated.
It has a mind of it's own. I don't control it - it
controls me (or tries to! ;-). I don't like that about
Project one bit. Is there any way to get it to stop
rearranging my resources? Also, it will insist I have a
resource conflict, when in reality there is none. When I
try to change the software to match reality, either it
won't let me, OR it changes the data I enter to some crazy
number.
I have varied from effort driven, to un-checking that box
on each task, but that makes no difference. Also, I have
tried changing the task type - from fixed
work-duration-units. No help.
More knowledgeable users, please advise me. What am I not
doing? What am I doing wrong. I'd like to give Project a
fair shake, but right now, IMHO, it's like the QuickBooks
of PM software!