A
andy
Hope someone can help,
I am trying to add a line ( similar to a status date line -Vertical) that
identifies a projected critical date.
i.e if i have a task that is due to finish 30 days from the start -so if it
started today 3rd of Oct it should finsh 1 Nov. I want to know where the 80%
date is from the 3rd and, show that as a vertical line down the project plan.
or is there a better way??
regards
andy
I am trying to add a line ( similar to a status date line -Vertical) that
identifies a projected critical date.
i.e if i have a task that is due to finish 30 days from the start -so if it
started today 3rd of Oct it should finsh 1 Nov. I want to know where the 80%
date is from the 3rd and, show that as a vertical line down the project plan.
or is there a better way??
regards
andy