J
Jena
Hi All,
I'm a bit lost and would appreciate your help.
I updated actual hours on several tasks, and the program updated the task to
be completed. The hours are only a portion of the planned hours, so I don't
understand why this is happening. When I try to change the % completed to
show that it is not yet done, the schedule changes - understandably -- but
not accurate to the plan prior to the incorrect update. I need to have the
plan showing the actual hours, and the correct hours remaining, with the
correct finish date for work yet to be completed, and can't seem to get there.
Any suggestions.
Thanks,
Jena
I'm a bit lost and would appreciate your help.
I updated actual hours on several tasks, and the program updated the task to
be completed. The hours are only a portion of the planned hours, so I don't
understand why this is happening. When I try to change the % completed to
show that it is not yet done, the schedule changes - understandably -- but
not accurate to the plan prior to the incorrect update. I need to have the
plan showing the actual hours, and the correct hours remaining, with the
correct finish date for work yet to be completed, and can't seem to get there.
Any suggestions.
Thanks,
Jena