D
DCBanks
I have task 1 linked to task 2 as a 'finish to finish' so they both finish on
the same day. Task 1 has a number of predecessors all with 'finish to start'
links. I want these predecessors to back off from task 1 so I have made them
all 'as late as possible' but they take that as the latest date on my whole
project. I want them to take the 'late as possible date' as being the Start
Date of task 1 - ie the one they are linked to.
I cant make the whole project ALAP as 95% is ASAP. In other words I want the
predecessors to be 'just in time'.
David
the same day. Task 1 has a number of predecessors all with 'finish to start'
links. I want these predecessors to back off from task 1 so I have made them
all 'as late as possible' but they take that as the latest date on my whole
project. I want them to take the 'late as possible date' as being the Start
Date of task 1 - ie the one they are linked to.
I cant make the whole project ALAP as 95% is ASAP. In other words I want the
predecessors to be 'just in time'.
David