JennPenn07
I am using PS2007 SP2 Feb CU
We level multiple project schedules on a weekly bases. In PS2003, the
leveling took no longer than approx 20min for 15 projects (leveling from
current week to 6mo out). In 2007 those same projects level for about two
hours. Has anyone had this problem? Any idea what the difference is between
the two versions that would cause such delay?
We level multiple project schedules on a weekly bases. In PS2003, the
leveling took no longer than approx 20min for 15 projects (leveling from
current week to 6mo out). In 2007 those same projects level for about two
hours. Has anyone had this problem? Any idea what the difference is between
the two versions that would cause such delay?