A
Atreides
As part of my project, most of the tasks are sequential and inter-linked (as
normal). However, I want to have some tasks sit separate from these tasks
because they are Project Management (PM) tasks. These tasks exists as
"support tasks" to the other tasks. For example, for every week that the
project runs, I will need 2 hours a week assigned to the "Project controls
and reporting" task.
Currently I've got it set up in a basic way. I've budgeted for a 6-week
project so my PM tasks are sitting at the top of the Gantt chart as 6-week
tasks. However, there are two obvious problems:
1. These tasks are set at 6 weeks, and the total duration of the rest of the
project is only about 5.5 weeks at the moment. This means that I am planning
to do 0.5 weeks of PM tasks after the project has already finished! How can I
restrict the end of this task? I've tried setting up a finish-finish
relationship with a "project complete" milestone task (one that is complete
once all the functional tasks are complete) but this moves the whole PM task
along. This seems strange to me since the task is not "fixed-duration".
2. Because these projects have the latest finish date and start on the
project start date, they all make up the critical path. However this doesn't
make sense, since they only are running while other tasks are running. How
can I exclude them from the critical path calculation?
How can I set up Project like this? I would imagine lots of people want to
do something similar to this.
Thanks
Atreides
normal). However, I want to have some tasks sit separate from these tasks
because they are Project Management (PM) tasks. These tasks exists as
"support tasks" to the other tasks. For example, for every week that the
project runs, I will need 2 hours a week assigned to the "Project controls
and reporting" task.
Currently I've got it set up in a basic way. I've budgeted for a 6-week
project so my PM tasks are sitting at the top of the Gantt chart as 6-week
tasks. However, there are two obvious problems:
1. These tasks are set at 6 weeks, and the total duration of the rest of the
project is only about 5.5 weeks at the moment. This means that I am planning
to do 0.5 weeks of PM tasks after the project has already finished! How can I
restrict the end of this task? I've tried setting up a finish-finish
relationship with a "project complete" milestone task (one that is complete
once all the functional tasks are complete) but this moves the whole PM task
along. This seems strange to me since the task is not "fixed-duration".
2. Because these projects have the latest finish date and start on the
project start date, they all make up the critical path. However this doesn't
make sense, since they only are running while other tasks are running. How
can I exclude them from the critical path calculation?
How can I set up Project like this? I would imagine lots of people want to
do something similar to this.
Thanks
Atreides