Å
åŠæ–°ä¸æ—§
Hi, our project manager is able to update the progress of their resource's
tasks, but can not update the progress of resource's milestone(duration 0
tasks). In this case, the resource can update his mile stone tasks and submit
to his PM.
My question:
- Can a project manager update progress for his resource's milestone tasks?
Thanks in advance,
JJin
tasks, but can not update the progress of resource's milestone(duration 0
tasks). In this case, the resource can update his mile stone tasks and submit
to his PM.
My question:
- Can a project manager update progress for his resource's milestone tasks?
Thanks in advance,
JJin