Project Manager not seeing hos own tasks in My Tasks

T

Tharmagon

All of the Team Members are seeing their tasks listed in My Tasks except the
Project Manager. As well as being the Project Manager he is also a Team
Member and has assigned some tasks to himself on several projects. But when
he goes to My Tasks nothinh is listed for any project.
 
D

Darrell

Tharmagon,

What have you checked so far?

I would begin with making sure the tasks were assigned to an enterprise
resource and not a local resource with a different spelling of the PM's name.

You may also want to repost this to the server newsgroup,
Darrell
 
T

Tharmagon

I will post on the server group as you suggested.

Although I am the admin for the server I am new to Project Server. So can
you tell me how to check that?
 
T

Tharmagon

I found the answer but I do nt know how it got like that. The Project Manager
was assigned to the project and Proposed not Committed. Is that a Resource
setting somewhere or did the Project Manager accidently set it for that
project only?
 