M
med111
I have this example in EPM 2007
a project manager PM creates a project p1 .in this project he define a
task t1 and create a team made of one resourece manager RM then he
publish and exit .RM can add more member to the team of the project in
fact he adds R1 and R2. then he saves and exits. the PM reopens P1
assign R1 and R2 to t1 set R1 as assignement owner for the tow
resource R1 and R2. Pm pulish p1
R1 receives 2 assignements in "My tasks" he makes updates and submits.
it is good until now!
But the PM receive only one update!! other update is received by RM .
Why???? I want that Pm receive the 2 updates!
a project manager PM creates a project p1 .in this project he define a
task t1 and create a team made of one resourece manager RM then he
publish and exit .RM can add more member to the team of the project in
fact he adds R1 and R2. then he saves and exits. the PM reopens P1
assign R1 and R2 to t1 set R1 as assignement owner for the tow
resource R1 and R2. Pm pulish p1
R1 receives 2 assignements in "My tasks" he makes updates and submits.
it is good until now!
But the PM receive only one update!! other update is received by RM .
Why???? I want that Pm receive the 2 updates!