Project measured in hours

D

David Morrison

I'm trying to create a Project plan for a system conversion that will be
taking place over the weekend. I need to view the project with a day/hour
timescale as opposed to dates. I've set my timescale to day/hour but can't
seem to figure out how to create tasks that begin at certain times of day.
How is this done?
 
G

Gérard Ducouret

Hello David,
In the Date and Start columns, you can display date + time :
Tools / Options / View / Date format : choose a date format suche as dd/mm/
yy 12:33 where 12:33 means haurs and minutes.

HTH

Gérard Ducouret
 
D

David Morrison

Thanks!

Gérard Ducouret said:
Hello David,
In the Date and Start columns, you can display date + time :
Tools / Options / View / Date format : choose a date format suche as dd/mm/
yy 12:33 where 12:33 means haurs and minutes.

HTH

Gérard Ducouret
 